Approximate quantities
A development of the elemental cost plan of estimating construction project costs, approximate quantities form part of an approximate quantities cost plan which represents a first attempt to measure defined quantities from drawings (or to ‘take them off’)
An approximate quantities cost plan is part of the iterative cost planning process and is a development of the elemental cost plan. Unlike the elemental cost plan (in which the cost of elements is broken down from the overall construction cost, based on the experience of the cost consultant and known costs of similar completed projects), the approximate quantities cost plan is a first attempt to measure defined quantities from drawings. In effect, it is a costed approximate bill of quantities.
The approximate quantities method is regarded as being more accurate and reliable than other estimating methods in showing where costs are distributed. In particular, it draws to the attention of designers those elements of the design that are standard and those that are not and which, as a consequence, may be more expensive.
Unlike the elemental method, the basis of the approximate method of estimating is the grouping together of diverse, combined items under a rate (known as a composite rate) which is calculated by combining the individual prices of the components in the group. Because the items grouped together have the same dimensions (whether in metres or square metres, or perimeter and area), it allows those items to be measured at the same time.
For example, under the approximate quantities method, items such as roofs can be grouped with soffits and ceilings; this would not occur in the elemental plan.
The approximate quantities cost plan can form a solid base for an effective value engineering exercise. However, it should be accompanied by a schedule of assumptions made and perhaps a cash flow projection. A pre-construction whole-life cost plan may also be prepared.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February